|
||||
![]() |
||||
Handy LinksSLAC TodaySLAC NewsLab News
SLAC Links
StanfordAround the Bay |
SAFE '08 Success Story: Power to the LCLS
The work was performed to feed power to a new substation for the LCLS project. Bringing power to the substation required cable splicing inside manholes, switching lines and conducting thorough inspections and tests along the way. "With qualified people backing you and proper planning, a lot can be done," said LCLS Facilities Electrical Engineer and Project Manager Lori Shewchuk. "Our objective is for everyone to go home safe." Before any electric work began, the team put tremendous effort into discussing the project's procedures and developing a work plan a week before it took place. "Everyone knew that this was going to take a great effort, and everyone's experience and opinions mattered," Shewchuk explained. "To make it all happen safely, and correctly, we needed to listen to each other."
"They really took their work planning and control to a whole new level," Department of Energy Environment, Health and Safety and Facility Operations Team Leader Tom Rizzi said. "It was very well done." The project did come to a halt for a few weeks when SLAC's high voltage electricians observed excessively loud buzzing coming from a control power transformer inside the substation. Because electricians suspected it was coming from the switchgear, the equipment that houses circuit breakers, they immediately suspended all work until the source—and thus the level of hazard—could be determined.
Compiling so many groups of people and including everyone in, from the beginning of planning, proved to be the key feature of the project's safety success. Everybody was on the same page and understood their roles and responsibilities. "We really pulled together a lot of resources to complete this activity," Shewchuk said. "We appreciate everyone's cooperation. Everybody’s efforts were so valuable." Matt Cunningham, SLAC Today, April 30, 2008 Top image, from left to right: Facilities Department Operations Electricians Lori Shewchuk, Karen Chan-Hui, Dumitru Ciorbea, Khalid Ahmed, Richard Maggi and Fred Jones. Not pictured are Charles McKenzie, Jose Regalado, John Blomdal, Mike Cook, Eddie Viray, Gerardo Lorenzo and James Kang. Center image: Twelve kilovolt lines in Manhole #49. (Click on image for larger version.) Bottom image: Electricians in breaker substation wearing electric arc flash protective equipment. (Click on image for larger version.) | |||
Last update: